Digging it in Boston: Central Artery's jacked tunnels helps cut $300 million in costs

Authors :
Green, Peter
Source :
ENR. August 19, 1996, Vol. 237 Issue 8, p24, 5 p.
Publication Year :
1996

Abstract

A redesign of Boston's Central Artery/Tunnel project saved $300 million in construction costs. In addition to the savings, the $14-million redesign will temporarily provide a place to cast immersed tunnel tubes and serve as jacking pits. Conceived by Maguire/Harris, the redesign improves the efficiency of the alignments. Jacking of two vehicle tunnels and a ramp tunnel also provide substantial savings in excavation costs.