Back to Search
Start Over
Fabrication of mock-up with Be armour tiles diffusion bonded to the CuCrZr heat sink
- Source :
- Fusion Engineering and Design. :321-324
- Publication Year :
- 2001
- Publisher :
- Elsevier BV, 2001.
-
Abstract
- The aim of this work is the manufacture of high heat flux mock-ups with Be armour tiles on a CuCrZr heat sink for fabricating the beryllium section of the divertor vertical target (DVT) in the ITER reactor. Diffusion bonding between the CuCrZr bar and the beryllium tiles was obtained by inserting an aluminium interlayer to accommodate surface irregularities as well as to provide a compliant layer for accommodating thermal mismatches during both manufacturing and operation and cycles.
Details
- ISSN :
- 09203796
- Database :
- OpenAIRE
- Journal :
- Fusion Engineering and Design
- Accession number :
- edsair.doi...........6f9a96fa8a075536f37afeac52acb20c