Study on Construction Resource Optimization and Uncertain Risk of Urban Sewage Pipe Network

Authors :
Xin Li
Jian Huang
Chunwei Li
Ning Luo
Wen Lei
Haiyuan Fan
Yuan Sun
Weiqi Chen
Source :
Periodica Polytechnica Civil Engineering.
Publication Year :
2021
Publisher :
Periodica Polytechnica Budapest University of Technology and Economics, 2021.

Abstract

With considering sewage pipe network upgrading projects in the “villages” in cities, the optimization of construction resources and the assessment of delay risks could be achieved. Based on the schedule-cost hypothetical theory, the mathematical model with constraint indicators was established to obtain the expression of optimal resource input, and conclude the method to analyze the schedule uncertainties. The analysis showed that cyclical footage of pipe could be regarded as a relatively fixed value, and the cost can be regarded as a function that depending on the number of working teams. The optimal number of teams and the optimal schedule occurred when the minimum total cost achieved. In the case of insufficient meteorological data, the Monte Carlo simulation method and uncertainty analysis method can be applied to assess the impact of rainfall on the total construction period, correspondingly the probability of such risk could be derived. The calculation showed that the risk of overdue completion varied significantly according to the construction starting time. It was necessary to take rainfall risk into consideration and make corresponding strategies and measures.

Details

ISSN :
15873773 and 05536626
Database :
OpenAIRE
Journal :
Periodica Polytechnica Civil Engineering
Accession number :
edsair.doi...........3d90e26fc2f289dde5d3d8ed8e6432d2
Full Text :
https://doi.org/10.3311/ppci.18877