Integrated job release and shop-floor scheduling to minimize WIP and meet due-dates

Authors :
Thom J. Hodgson
Denis Cormier
Andrew Zozom
Russell E. King
Alexander J. Weintraub
Source :
International Journal of Production Research. 41:31-45
Publication Year :
2003
Publisher :
Informa UK Limited, 2003.

Abstract

We address the problem of releasing jobs to the factory floor while meeting delivery dates and minimizing the work-in-process inventory. Heuristic algorithms were developed that used an efficient, detailed shop-floor scheduling model to determine the release times of new jobs. The process starts with the current shop floor conditions and determines the sequencing of both in-process and new jobs on machines in order to minimize the maximum lateness (L max ). The approach is tractable for industrial-sized problems and provides solutions close to a calculated lower bound for WIP. Computational experience is given.

Details

ISSN :
1366588X and 00207543
Volume :
41
Database :
OpenAIRE
Journal :
International Journal of Production Research
Accession number :
edsair.doi...........2932e5161c0bce3ed5a4043e53272e0b