Mechanical Pole Testing Using Partial Load Force for Application in Electric Utilities

Authors :
F C Chan
Gordon M S Woo
Kris Deuar
Source :
HKIE Transactions. 13:1-9
Publication Year :
2006
Publisher :
The Hong Kong Institution of Engineers, 2006.

Abstract

The transmission and distribution networks of electric utilities normally consist of overhead lines and underground cables. For distribution overhead lines conductors are supported by poles which are usually made of wood, steel or reinforced concrete. The design life of these poles is in the range of 20 to 50 years. It is necessary to test and confirm that adequate levels of safety and reliability can be maintained throughout the remaining life when the facilities have been operated for more than 10 years. Safety to work on poles as well as public safety can be dramatically enhanced if all poles are periodically inspected and mechanically tested in order to prove that they are capable to withstand the worst operating conditions such as severe typhoon, hurricane, cyclone and the like.This paper describes an innovative and non-destructive approach, namely the ‘Mechanical Pole Testing’ (MPT) with partial load force, to evaluate the pole strength in a cost-effective manner. The Mechanical Pole Testing method ...

Details

ISSN :
23263733 and 1023697X
Volume :
13
Database :
OpenAIRE
Journal :
HKIE Transactions
Accession number :
edsair.doi...........17069d2154b014b85f5cd08ee430a52d