Comparative Analysis of Planning with the Critical Path Method, Last Planner System, and Location-Based Techniques in Brazil, Finland, and the United States

Authors :
Scala, Natalie M.
Schiavone, Vincent
Olivieri, Hylton
Seppänen, Olli
Alves, Thais da C. L.
Liu, Min
Granja, Ariovaldo Denis
Source :
Engineering Management Journal; July 2023, Vol. 35 Issue: 3 p237-256, 20p
Publication Year :
2023

Abstract

AbstractThe Critical Path Method (CPM), the Last Planner System (LPS) and location-based methods, such as the Line of Balance (LB), are discussed extensively in the technical literature about schedules. However, no discussion exists focusing on the differences and similarities of these methods in terms of their use in different countries. Using chi-squared and Fisher’s exact tests, this research compared three countries (Brazil, Finland, and United States) and the methods to evaluate both intra- and inter-country implementation to gain additional insights about their use. Results suggest statistically significant intra- and inter-country differences regarding how these methods are used, with a specific focus on mechanics in the countries, offering important information to address their various scheduling needs. The results reflect the current state of practice; engineering and construction managers should understand different ways of understanding scheduling. Such understanding can lead to more efficient communication with collaborators and when incorporating foreign teams in projects. The study identifies the need for further scientific explanation as to why these methods are used in the manner they are intra-country as well as adaptions made in inter-country relationships.

Details

Language :
English
ISSN :
10429247 and 23770643
Volume :
35
Issue :
3
Database :
Supplemental Index
Journal :
Engineering Management Journal
Publication Type :
Periodical
Accession number :
ejs63811316
Full Text :
https://doi.org/10.1080/10429247.2022.2069981