Construction of shallow buried large-span metro stations using the small pipe roof-beam method.
- Source :
- Frontiers of Structural & Civil Engineering; Jan2024, Vol. 18 Issue 1, p122-136, 15p
- Publication Year :
- 2024
-
Abstract
- In relation to the Shifu Road Station project on Line 4 of the Shenyang Metro in China, a small-pipe roof-beam method for constructing subway stations is presented. First, a numerical simulation was performed to optimize the supporting parameters of the proposed method and determine the design scheme. Subsequently, the deformation of the pipe roof and surface settlement during the construction process were investigated. Finally, the surface settlement attributed to the excavation was studied through field monitoring, and the proposed method was compared with other methods. The results show that an increase in the pipe-roof spacing has little effect on the surface settlement and pipe-roof deformation. The bearing capacity of the pipe roof can be efficiently utilized once the flexural stiffness reaches 2EI, and the flexural stiffness is not the dominant factor controlling the deformation. The essential stages in controlling surface settlement are the excavations of the transverse pilot tunnels and the soil between them. The final settlement value of the ground was 24.1 mm, resulting in a reduction in the construction period by at least five months while satisfying the control requirements. [ABSTRACT FROM AUTHOR]
- Subjects :
- SUBWAY stations
PIPE
TUNNELS
COMPUTER simulation
Subjects
Details
- Language :
- English
- ISSN :
- 20952430
- Volume :
- 18
- Issue :
- 1
- Database :
- Complementary Index
- Journal :
- Frontiers of Structural & Civil Engineering
- Publication Type :
- Academic Journal
- Accession number :
- 177538220
- Full Text :
- https://doi.org/10.1007/s11709-024-1008-z