Abstract

The new metro line in Thessaloniki includes, besides the excavation of two twin tunnels, the construction of 13 stations with central platform in settlement-reducing top-to-down construction method. Due to restrictions in available space, it was necessary to dispense with the construction of an inner shell. Further constraints were the soft and highly inhomogeneous soil, the large excavation depths in groundwater, and the earthquake-resistant design of the structures. The special foundation works executed for permanent uplift safety as well for the soil strengthening in front of the excavation walls are described for representative stations. Die neue U-Bahn in Thessaloniki umfasst, neben dem Schildvortrieb zweier Röhren, die Errichtung von 13 Bahnhöfen mit zentralem Bahnsteig in verformungsarmer Deckelbauweise. Wegen der engen Platzverhältnisse musste dabei auf eine Innenschale verzichtet werden. Weitere erschwerende Randbedingungen sind der weiche, stark inhomogene Untergrund, die große Aushubtiefe im Grundwasser und die erdbebengerechte Auslegung der Tragkonstruktion. Für typische Bahnhöfe werden die Spezialtiefbaumaßnahmen zur dauerhaften Auftriebssicherung sowie zur Verstärkung des Fußwiderlagers der tiefen Baugruben vorgestellt. [ABSTRACT FROM AUTHOR]

Details

Language :
English
ISSN :
18657362
Volume :
6
Issue :
5
Database :
Academic Search Index
Journal :
Geomechanik und Tunnelbau
Publication Type :
Academic Journal
Accession number :
90526458
Full Text :
https://doi.org/10.1002/geot.201300024