Uncertainty in Task Duration and Cost Estimates: Fusion of Probabilistic Forecasts and Deterministic Scheduling.

Authors :
Khamooshi, Homayoun
Cioffi, Denis F.
Source :
Journal of Construction Engineering & Management. May2013, Vol. 139 Issue 5, p488-497. 10p.
Publication Year :
2013

Abstract

A model for project budgeting and scheduling with uncertainty is developed. The traditional critical-path method (CPM) misleads because there are few, if any, real-life deterministic situations for which CPM is a great match; program evaluation and review technique (PERT) has been seen to have its problems, too (e.g., merge bias, unavailability of data, difficulty of implementation by practitioners). A dual focus on the distributions of the possible errors in the time and cost estimates and on the reliability of the estimates used as planned values suggests an approach for developing reliable schedules and budgets with buffers for time and cost. This method for budgeting and scheduling is executed through either simulation or a simple analytical approximation. The dynamic buffers provide much-needed flexibility, accounting for the errors in cost and duration estimates associated with planning any real project, thus providing a realistic, practical, and dynamic approach to planning and scheduling. [ABSTRACT FROM AUTHOR]

Details

Language :
English
ISSN :
07339364
Volume :
139
Issue :
5
Database :
Academic Search Index
Journal :
Journal of Construction Engineering & Management
Publication Type :
Academic Journal
Accession number :
86929019
Full Text :
https://doi.org/10.1061/(ASCE)CO.1943-7862.0000616